Summary
On September 20, 2013 a small subset of CRM Online organizations served from North American datacenters were inaccessible. Microsoft Service Engineering team investigated and restored service. The service incident affected less than 1% of customers in the region.
Customer Impact
Impacted customers could not access their CRM Online organizations.
Incident Start Date and Time
September 20, 2013 06:45 AM PDT (UTC-7)
Date and Time Service was Restored
September 20, 2013 08:00 AM PDT (UTC-7)
Root Cause
Impacted organizations lost connectivity with their databases due to a SQL Availability Group failure. The investigation determined that the primary Availability Group (AG) was in an unhealthy state and failover did not work correctly on the secondary AG.
Next Step(s)
Issue | Next Step | Team Owner | Timeline |
SQL Failure | CRM Service Engineering team is investigating the root cause of this failure and will work with the Microsoft SQL team to determine how we prevent it in the future. | Dynamics Service Engineering (DSE) team - CRM Online | In progress |